Since installation in the fall, the P removal structure is still currently removing >90% of the cumulative dissolved P that has flowed into it. Please see the following link for a recent presentation: http://dasnr.adobeconnect.com/p7kmw6j1uwt/
A step by step description of the design and construction of a phosphorus (P) removal structure. Contact: Dr. Chad Penn (chad.penn@okstate.edu) and Dr. Josh McGrath (josh.smyrna@gmail.com)
Monday, May 12, 2014
Monday, March 17, 2014
New published paper on structure design
This paper is open access at the Journal of soil and water conservation. It summarizes much of the information in this blog regarding how to design a P removal structure tailored to a specific site.
We will continue to update this blog with results from the P removal structure.
We will continue to update this blog with results from the P removal structure.
Wednesday, March 5, 2014
First field day presentation of poultry farm structure and update
Field day announcement
There will be a field day presentation of the poultry farm runoff P filter on May 23rd, 2014 in Westville, OK. The flyer and schedule of events is shown here. Hope to see you there! Please contact me for any additional information or questions.
Current performance of the structure
Since completion of the P removal structure last fall there has been very little precipitation here. Thus far there has been only two events that have produced runoff at the site. Both sets of samples showed nearly 100% P removal. Due to problems with our connectivity to the automatic samplers, we cannot state what the flow rates were. However, we will manually download the data to determine flow rates and duration.
Thursday, October 17, 2013
Installation and sieving of steel slag
Before pouring slag into the structure, it was necessary to
sieve the material to > ¼”. This was
done on a large scale at a gravel quarry next door to the steel mill located in
Ft. Smith, Arkansas. A liner was placed
on the bottom of the structure before dumping the sieved material into it. A liner was also placed on the outflow side of
the structure (i.e. “apron”) in order to channel all of the treated water into
the flume for monitoring purposes.
The sides of this outflow apron were constructed with
railroad ties. In the above picture they
are covered with the liner.
The perforated drainage pipes were placed at the floor of
the structure (on top of the liner) before covering it with the sieved
slag. Note that these drainage pipes
channel water to the outlet of the structure, which is comprised of expanded
metal. Between 35 and 40 tons of slag
was dumped into the structure use a skid steer:
We ran out of sieved slag near the end, so we had to sieve
around 10 tons of slag to produce 6 more tons of >1/4” slag. I’m pretty irritated in the picture below because
the concrete vibrator that was used to screen the material kept breaking all of
our U-bolts:
Eventually we ran out of U-bolts and we cleaned out the
local hardware store for U-bolts. At
that point we had to sieve it the old fashioned way. The guy on the right is Stan Roberts, a
salesman from Automatic Engineering, the distributor for ISCO auto samplers in
Oklahoma. Stan was supposed to stop by to
help with programming…..hahaha, but we put him to good use since we were not
yet ready for programming. That is a
good salesman right there. Steps out of
the office and does some “hands on” work with no complaints.
During the installation, we forgot to stabilize the
downstream “gate”. After it was filled
with slag, the metal started to bow. Note
that the wood in the picture below was temporary. It was removed after the slag was treated
in-situ.
We managed to remove the bow in the metal gate using a
come-along and 40 feet of chain. After we
pulled it back, we stabilized it by pounding several ½” rebar into metal
sleeves welded to the gate. I wish I had
a picture of that process because it was pretty awesome. Again, the slag was treated in-situ. The samplers were set up (which is what we called
Stan for!) and were placed in their own respective buildings:
We rolled out some erosion control mats and seeded uphill of
the structure. Trimmed the excess
liner. We also built a new suction head
for the samplers to be able to handle a very shallow depth of water.
At this point we are ready to collect samples! Just offhand, I hope that we can have a field
day presentation in January. We will
continue to update this blog with results.
Wednesday, September 18, 2013
Preparing the Structure for Slag and Monitoring
The ISCO automatic samplers have finally arrived along with
the flow monitoring equipment. The flow
and sample monitoring will be observed remotely at our office in Stillwater through
the purchasing of a Verizon data plan.
Basically, we will be able to monitor what the samplers are
doing/measuring at any time. This way,
when there is a flow event, we will know it immediately and obviously know to
go to the site to collect the sample bottles as soon as possible for laboratory
analysis.
We recently poured some concrete at the inflow side of the
structure. The picture below shows the “before”
picture and you can see that the inflow pipes (black) are at varying elevation
from the surface, which is bare soil. We
wanted to create a clean and level “apron” where the inflow runoff water can
enter the structure. Eventually, there
will be perforated plastic pipe attached to the other side (inside the
structure) of the black metal pipe. This
pipe will be buried in the slag and will serve to evenly distribute the
inflowing water (i.e. serve as a manifold).
The next pictures show the concrete work:
Also on this site visit we can to lay the pipe which will hold the suction lines for the automatic samplers and the bubbler tube for the flow monitor.
Not very exciting.
However next week we will sieve the slag and put it in the structure and
finish up the installation of the monitoring equipment.
I would like to briefly highlight the work by Dr. Stefan Jansen in The Netherlands, here.
Friday, August 30, 2013
Flume installation and preparation for monitoring: Part 1
This portion of the construction and installation process
for the P removal structure is NOT necessary for the typical-everyday use. What is described here is for very detailed
monitoring of performance for the purpose of research. It is completely unnecessary for the applied
purpose of the P removal structure. We
are doing this so that we can demonstrate the effectiveness of the unit and
also produce more data for model verification.
This section is mostly relevant to researchers.
That being said, we will not put the PSM (treated steel slag
in this case) into the structure until all the monitoring equipment is
installed. For monitoring, our purpose
it to measure the amount (volume) of runoff treated by the structure during
each runoff event and also measure the P concentrations flowing in (i.e. before
treatment) and after (i.e. after treatment).
Knowing this, we can then estimate how much (mass) P has been trapped by
the P removal structure.
On the “inflow” side of the structure where water will
enter, we will use an ISCO automatic sampler that will be triggered to collect
samples based on the detection of flow at the “outflow” side of the structure
where the treated water will be located.
Below you can see some photos of the construction of the approach for
the 3 foot flume that will be used to monitor flow rate.
Monitoring flow rate is critical if one is serious about
getting a real estimate on the P removal performance of a P removal
structure. Many researchers have
utilized only water sampling in their monitoring regime without the use of flow
monitoring. Simply put, P concentration testing
of the treated water compared to untreated water alone is not sufficient for
assessing the capacity of a P removal structure; knowledge of the flow rates
and therefore the volumes of water treated is absolutely critical. Any assessment without the use of detailed
and thorough flow monitoring should not be taken too seriously. Why? The short answer is “P load”. If I measure a 100% P concentration reduction
and there is only 1000 gallons of water treated, it is not correct to compare
that concentration reduction to another scenario where there is only 50% P
concentration reduction and 1 million gallons of water treated. Simply put, the most important factor is the
P load (i.e. mass) reduction. Instead,
it is more correct to compare the P load reduction (i.e. mass of P removed).
Too often, we focus on the final concentration of runoff
water and treated water. This makes little
sense, especially when surface water quality thresholds (i.e. critical P
concentrations for streams and lakes) are applied to the context of runoff
water concentrations. For example,
runoff concentrations from a certain field (call it field 1) may test at 1 mg
P/L, while field 2 may produce 0.2 mg P/L.
That does not mean that field 2 is somehow more “safe” than field
1. Consider a scenario where field 1
produces 2 million L runoff for an event, while field 1 only produces 1000
L. The P load transported off site for
field 1 and 2 would be 1 g vs 400 g, respectively. Concentrations alone would be deceiving in
that case. What matters is the mass or
load of P that reaches the lake or stream; concentrations (mass/volume) change
with dilution, evaporation, etc., but it is the mass of P that does not
change. This is why the USEPA has moved
to a “total maximum daily loading”, or TMDL system for point and non-point
source pollution concerning nutrients.
For the same reasons, it is important to assess the
performance of a P removal structure based on P load reduction, not P
concentration reduction.
Below you can see the flume installation process.
This flume can handle much more water than our projected 2
yr storm (~16 cfs). This flume is being
used courtesy of Dr. Sherry Hunt, Kem Kadavy, and Ron Tejral, located at the
USDA-ARS Hydraulics Engineering Research Unit.
All of the treated water plus any water that might overflow
the structure will flow through the flume for measurement. There will not be any water overflowing the
structure if none of the storms exceed a 2 yr return period for that
location. In addition, if that does
happen, there will be a flow sensor (actually a depth sensor) placed on top of
the structure that will also monitor exactly how much water overflows the
structure and remains untreated. Below is
the view looking from the structure downhill toward the flume:
This area between the outflow drainage of the structure and the flume will have an impermeable liner placed on the ground and “bordered” with stabilized railroad ties to force all water from the structure to flow through the flume where flow rate will be monitored and also where samples will be taken by the ISCO sampler.
The photos below show the installation of the small building that will house the ISCO sampling equipment:
Wednesday, August 14, 2013
Construction and Installation of the Structure
Several posts back we determined how much PSM
(treated slag in this case) was required to meet our P removal goals at this
site, and we also determined how to orient that slag (i.e. area and depth) at
our site to be able to treat all the runoff from a 2 yr-24hr storm event.
Now it is time to build the structure. In this case we are going with the low-tech,
standard box structure where water flows through the PSM from the top-downward
into subsurface drainage pipes. With one
small twist however: the drainage pipes at the bottom of the structure will not
protrude through.
We also designed our structure to be easily cleaned
out with a front-end loader or a skid-steer.
Here is most of the structure in pieces as we take
it to the shop for painting:
Getting the primer on:
Then the paint:
Heavy, but not so heavy that we could not lift them
by hand. Shown in the picture is Stuart Wilson – technician, Alexandre Ricardo Alves
(i.e. The Shark) – Brazilian student intern, and Josh Daniel – graduate student.
Putting the pieces into our previously made “footprint”. Note the adviser is actually working the
shovel.
It was wet that day:
Completely put together: Note the earthen berms meet
at the entrance to the structure:
Total cost for the metal materials and for a private
fabrication shop to custom construct to our specification: $2,500.
Powerhouse, in Stillwater, OK.
405-377-6396. They did an excellent job.